Recreational Eagle Center Addition
A page within Recreational Eagle Center Addition
This project includes design and construction of a 35,200 SF addition to the Recreational Eagle Center. This includes an enlarged strength training space, large multipurpose recreation room and other related support spaces including changing areas and toilet rooms. There is also a 5,200 SF basement under a portion of the addition to provide storage of recreation equipment and to allow mechanical access from the existing building to the addition.
At a glance...
Project Budget
The project budget is $8.6 million.
Project Number
The DFD Project Number is 14I2B.
Current Status
The project is complete.
Building Size
The addition is 35,200 SF on two levels, with 5,200 of basement.
Location
The location of the addition is the southwest corner of the Recreational Eagle Center.
Timeline
This project is scheduled to begin the design phase in 2016 and construction was completed fall 2018.